What is a routing and what is a work centre?
A routing is the ordered list of operations needed to make an item: cut, bend, weld, paint, inspect, each with its work centre and expected setup and run time. A work centre is a machine, cell or group of similar resources with a capacity in hours and a cost rate per hour. Together they tell the shop where a job goes next and what its labour should cost.
By Arunkumar V, CTO · 03 November 2026 · 2 min read
- manufacturing routing
- work centre definition
- routing vs BOM
- work centre rate
What a routing contains
The routing is to labour what the BOM is to material. A work order copies the routing at release, so later changes to the master routing do not disturb jobs already running. Times on the routing are the plan; times logged by operators are the actual.
- Operation number and description, in sequence
- Work centre for each operation
- Setup time, run time per unit, and any queue or move time
- Instructions or a reference to a work instruction and drawing
- Inspection points and whether the operation can be subcontracted
- Alternate work centres, where the operation can move under load
What a work centre is
A work centre is a planning and costing unit. It can be one machine, such as a laser cutter, a group of interchangeable machines, such as three manual lathes, or a manual cell, such as the welding bay. Each has a capacity, usually hours per day times the number of resources, and a rate per hour that covers the operator, the machine's depreciation and power and often a share of overhead. The rate is what turns logged hours into job cost. Setting work centres too fine, one per person, makes scheduling impossible; too coarse, one for the whole shop, makes the cost rate meaningless. One per distinct process or machine group is the usual rule.
Routing versus BOM
Some systems combine the two into a single production template. That is fine for simple parts. When one part can be made on either the laser or the punch depending on load, you want one BOM and two routings, so keep the records separate in your head even if the software merges them.
| Question | BOM | Routing |
|---|---|---|
| What does it list | Materials and quantities | Operations and times |
| Where is it done | Not stated | Work centre per operation |
| Drives | Purchasing, material issue, material cost | Scheduling, labour logging, labour cost |
| Changes when | Design or material changes | Method, machine or time changes |
| Owner | Engineering or production | Production |
Why small shops should bother
A shop that runs on memory does not need routings written down until the day the person with the memory is away. Beyond that, routings and work centres earn their keep in three ways. They let a job card print with the steps in order, so a new operator can follow it. They let labour be logged where it happens, so a job cost shows that bending took twice the quoted time. And they let you see load by work centre, which is the first honest view of capacity most owners get. Start with the current method for your top products, use round numbers for times, and correct them from logged actuals rather than trying to time-study everything first.
Where ZMOS fits
ZMOS work orders carry routing steps and work centres. Labour is logged at the work centre through barcode job cards, and job costing applies the work-centre rate to logged hours, reporting material plus labour per job and per unit when the job closes. Job work (subcontracting) is supported for operations done outside. It is built for sheet-metal, machining and fabrication shops of 10 to 50 people. If you need finite capacity scheduling across many machines and shifts, test that specifically before choosing it; the core is costing and tracking rather than advanced scheduling.
People also ask
Short answers, each one complete on its own.
Related answers
- What is a bill of materials?
- What is a work order in manufacturing?
- What is job costing in manufacturing?
- How do I track labour hours on jobs?
- What is a job card in manufacturing?
- What is WIP inventory?
- What is a manufacturing ERP?
- What is a manufacturing operating system?
- All 54 answers
Inside ZMOS
What is the difference between a work centre and a machine?
A machine is a physical asset. A work centre is the planning unit the software schedules and costs against. It can be one machine, several interchangeable machines or a manual bench. Group machines into one work centre when any of them can do the operation equally well.
How do I set a work-centre rate?
Add the operator's loaded hourly cost to the machine's hourly cost (depreciation, power, tooling, maintenance), then add a share of overhead if you apply overhead that way. Divide annual figures by productive hours, not calendar hours. Review once a year and after any major purchase.
What is setup time versus run time?
Setup time is the fixed time to prepare the work centre for the job, such as loading a program and tooling, regardless of quantity. Run time is the time per unit once running. Separating them lets the routing cost small batches correctly, where setup dominates.
Should routing times come from time studies?
Not at first. Use the supervisor's estimate, release the routing, and compare against logged actuals after a few jobs. Adjust the routing where the gap is consistent. Formal time studies are worth it only for high-volume repeat parts where a few seconds per unit matter.
See it on your own stock and jobs
ZMOS is free for six months for startups and registered partners, no card. Or ask an engineer anything on WhatsApp; we reply within 6 hours in working hours.