# WIP Inventory: How to Calculate and Track Work in Progress

Work in progress is the money sitting on the shop floor in jobs that have started and not finished. The formula is one line. The useful part is proving the figure job by job, and seeing which jobs have stopped moving.

By [Arunkumar V](https://zudoworks.com/about/arunkumar-v/), founder and CTO of Zudo Works
22 November 2026 · 13 min read

## Quick answer

WIP inventory, work in progress or work in process, is the cost of jobs that have started but are not finished: material issued, labour logged and overhead applied. Closing WIP = opening WIP + manufacturing costs added in the period − cost of jobs completed. Check the result against a list of open jobs. The two totals should match.

![WIP inventory, work in progress. Four stages as arrows: raw material held in the store, issued to a job where value enters WIP, work in progress made of material, labour and overhead, and finished goods where value leaves WIP. Closing WIP equals opening WIP plus costs added minus cost of jobs completed. Worked example with invented figures: 18,400 plus 84,700 minus 79,500 equals 23,600, which is 9.2 WIP days](https://zudoworks.com/Asset/img/insights/wip-inventory-work-in-progress.webp)

How value moves into and out of work in progress, with the closing figure from the worked example. The figures are invented to show the arithmetic.

## On this page

1. [The short answer](#short-answer)
2. [What WIP inventory means](#meaning)
3. [The WIP inventory formula](#formula)
4. [A worked month](#worked-example)
5. [Prove it with the open-job list](#open-job-check)
6. [Two measures worth watching](#wip-days)
7. [What the Australian and New Zealand rules say about cost](#au-nz)
8. [How to track WIP in a small shop](#track)
9. [How ZMOS tracks work in progress](#zmos)
10. [How to reduce WIP](#reduce)
11. [What to take from this](#summary)
12. [Frequently asked questions](#faq)

Walk through any fabrication or machining shop and you will pass money on trolleys. Cut blanks waiting for the press brake. A welded frame waiting for paint. A batch of brackets held up because the fasteners have not arrived. Every one of those has been paid for in steel and wages, and none of it can be invoiced yet. That is work in progress, and for many small manufacturers it is the largest figure on the balance sheet that nobody can explain.

This guide is written for manufacturers of roughly 10 to 50 people in Australia and New Zealand. It covers what WIP inventory is, the formula, a worked month, the check that proves the figure, two measures that show whether WIP is healthy, what the local accounting and tax pages say about cost, and how open jobs are tracked in ZMOS. Outside sources were checked on 22 November 2026 and are linked where they are used. It is general information, not accounting or tax advice.

## The short answer

- **WIP inventory is the cost of jobs started but not finished.** Material issued to the job, labour logged on it and any overhead you apply.
- **The formula:** closing WIP = opening WIP + manufacturing costs added − cost of jobs completed.
- **Prove it from the floor.** Add up the cost to date of every open job. That total should equal the formula. If it does not, something was posted to one and not the other.
- **Watch two things each week:** WIP days, and the age of the oldest open jobs.
- **Work in progress and work in process mean the same thing** in a factory. Both shorten to WIP.
- **Most excess WIP is waiting, not working.** Jobs released before the material, drawing or customer decision was ready.

## What WIP inventory means

A manufacturer’s stock is in one of three states. Raw material and bought-in parts sit in the store. Finished goods sit on the despatch shelf. Everything between those two points is work in progress: material that has been issued to a job, with whatever labour and overhead has been added to it so far.

The boundary matters. A sheet of steel in the rack is raw material even if a job is planned for it. It becomes WIP at the moment it is issued to a work order. A finished part is still WIP until the job is completed and the part is received into stock. Shops that are loose about those two moments get a WIP figure that drifts, because material leaves the store without a job to carry it, or finished parts ship while the job is still open.

On the terms: Australian, New Zealand and British accountants usually say work in progress, and American sources usually say work in process. Software vendors use both, sometimes on the same page. In a factory they mean the same thing. Our shorter page on [what WIP inventory is](https://zudoworks.com/answers/what-is-wip-inventory/) covers the definition on its own.

## The WIP inventory formula

**Closing WIP = opening WIP + manufacturing costs added − cost of jobs completed**

Each part has a plain meaning.

| Term | What it is | Where the figure comes from |
| --- | --- | --- |
| Opening WIP | The closing WIP of the period before. | Last month’s figure |
| Material added | Material issued to jobs in the period, at cost, less anything returned to the store. | Stock issues against work orders |
| Labour added | Hours logged on jobs multiplied by the hourly rate. | Job cards or time sheets |
| Overhead added | A share of factory running costs, if you apply one. Many small shops use a percentage of labour or a rate per machine hour. | Your costing rule |
| Cost of jobs completed | The full cost of every job finished into stock or shipped in the period. Textbooks call it cost of goods manufactured. | Closed jobs |

The inventory software vendors whose guides rank for this term, Unleashed and QuickBooks among them, give the same formula in slightly different words. What those guides tend to leave out is the second half of the job: checking the answer against the floor.

## A worked month

The figures below are invented to show the arithmetic. Read them in your own currency. A fabrication shop starts October with 18,400 of work in progress.

| October | Amount |
| --- | --- |
| Opening WIP | 18,400 |
| Material issued to jobs, less returns | 52,300 |
| Labour logged on jobs | 21,600 |
| Overhead applied at 50 per cent of labour | 10,800 |
| Manufacturing costs added | 84,700 |
| Cost of jobs completed | 79,500 |
| Closing WIP | 23,600 |

Closing WIP = 18,400 + 84,700 − 79,500 = **23,600**.

WIP rose by 5,200 in the month. That is 5,200 of cash paid out for steel and wages that has not yet turned into something the shop can invoice. Whether that is a problem depends on why. A large job started in the last week is normal. Four jobs stuck for a fortnight is not.

## Prove it with the open-job list

The formula gives you a number from the accounts. The floor gives you the same number a second way: list every job that was open at month end and add up what has gone into each.

| Job | Material | Labour and overhead | Cost to date |
| --- | --- | --- | --- |
| 1041 | 6,200 | 3,150 | 9,350 |
| 1044 | 4,800 | 2,100 | 6,900 |
| 1047 | 3,900 | 900 | 4,800 |
| 1050 | 2,550 | 0 | 2,550 |
| Total | 17,450 | 6,150 | 23,600 |

Labour and overhead are shown together to keep the table short. Overhead is 50 per cent of labour, as in the month above. The list totals 23,600, the same as the formula. When the two agree, you can trust both. When they do not, the difference is nearly always one of these:

- Material taken from the store without being issued to a job.
- Material issued to the wrong job, or issued twice.
- Hours worked but not logged, or logged against a general code.
- A job that shipped and was invoiced but never closed, so its cost is still counted as WIP.
- Scrap thrown away without being written off the job.

This reconciliation is the most useful month-end check a small shop can run, and it takes minutes once issues and hours are recorded against jobs as they happen. Look at Job 1050 as well. It has material and no labour. Either it was issued on the last day of the month, or material was pulled early for a job that could not start. The list shows it. The formula never would.

## Two measures worth watching

### WIP days

WIP days turns the balance into time: how many days of production are sitting on the floor.

**WIP days = closing WIP ÷ cost of jobs completed in the period × days in the period**

For the example: 23,600 ÷ 79,500 × 31 = **9.2 days**. There is no universal target, because a shop building machines to order will carry far more than one stamping simple brackets. What matters is your own trend. If WIP days climb while output stays flat, jobs are taking longer to get through, and customers will feel it as late deliveries before the accounts show it.

The link between WIP and lead time is known as Little’s law: average WIP equals throughput multiplied by lead time. Counted in jobs, a shop that completes three jobs a day and has twelve open has an average lead time of four days. Release more jobs than the shop can finish and the lead time of every job grows. That is why cutting WIP is one of the surest ways to [reduce manufacturing lead time](https://zudoworks.com/manufacturing/guides/reduce-manufacturing-lead-time/), and why it shows up in delivery scores such as [DIFOT](https://zudoworks.com/insights/difot-delivery-in-full-on-time/).

### WIP ageing

Sort the open jobs by the date they started and put them in bands.

| Days since first issue | What it usually means | What to do |
| --- | --- | --- |
| Within your normal lead time | The job is moving. | Nothing |
| Up to twice your normal lead time | Waiting for a part, a machine or an answer. | Find out which, and name an owner |
| More than twice | Stalled. Often a customer hold, a quality problem or a job everyone forgot to close. | Decide: finish it, close it or write it off |

Set the bands from your own lead times. A job that has been open for three times its normal lead time is rarely worth what the books say. The standard described in the next section requires stock to be carried at the lower of cost and what it can be sold for, so old WIP is also an accounting question.

## What the Australian and New Zealand rules say about cost

What goes into the cost of WIP is not only a management choice. Three official pages are worth knowing. This is a summary of what they say, read on 22 November 2026. Ask your accountant how they apply to you.

**The accounting standard.** [AASB 102 Inventories](https://standards.aasb.gov.au/node/619) says inventories are measured at the lower of cost and net realisable value (paragraph 9). The costs of conversion include direct labour and a systematic allocation of fixed and variable production overheads (paragraph 12). Fixed overheads are allocated on the normal capacity of the plant, the amount per unit is not increased because production was low or plant was idle, and unallocated overheads are expensed in the period (paragraph 13). Cost is assigned by first-in, first-out or weighted average (paragraph 25). In plain terms: a quiet month does not make your WIP worth more.

**Australian tax.** The ATO’s page on [valuing trading stock](https://www.ato.gov.au/businesses-and-organisations/income-deductions-and-concessions/income-and-deductions-for-business/accounting-for-trading-stock/valuing-trading-stock) lists three methods: cost price, market selling value and replacement value. It says a different method can be chosen each year for different items, and that cost price includes all costs associated with bringing the stock to its current condition and location. The page does not deal with part-finished jobs specifically, so that is a question for your accountant.

**New Zealand tax.** Inland Revenue’s page on [valuing trading stock](https://ird.govt.nz/income-tax/income-tax-for-businesses-and-organisations/types-of-business-income/trading-stock/valuing-trading-stock) lists four methods: cost, discounted selling price, replacement price and market selling value. It says cost includes purchase price, import duties, manufacturing costs, inwards freight and overheads, and that a business using first-in, first-out or weighted average must use the same cost-flow method as in its financial statements. It also describes concessions for low-turnover traders, defined there as sales of less than 3 million dollars for an income year.

The practical point for a small shop: management WIP of material plus labour is enough to run the floor, but the year-end figure may need overhead added. Agree the method with your accountant once and keep it the same every year.

## How to track WIP in a small shop

Tracking WIP is four habits. None of them needs special software, though software makes them stick. Our short answer on [how to track WIP on the shop floor](https://zudoworks.com/answers/how-to-track-wip/) covers the same ground in brief.

- **Every issue names a job.** No material leaves the store without a work order number. Returns come back against the same job.
- **Hours are logged the day they are worked.** Against the job and the operation, not rebuilt from memory on Friday.
- **Jobs are closed the day they finish.** Receive the finished parts into stock and close the work order. An open job with nothing left to do inflates WIP.
- **Scrap is written off the job.** With a quantity and a reason, so the cost leaves WIP and shows up as scrap.
- **Jobs are released only when ready.** Material on hand, drawing at the right revision, customer details confirmed. See our guide to [BOM revision control](https://zudoworks.com/insights/bom-revision-control/).
- **The open-job list is reviewed weekly.** Oldest first. Each stalled job gets an owner and a date.

## How ZMOS tracks work in progress

[ZMOS](https://zudoworks.com/zmos/) is our manufacturing system for shops of 10 to 50 people. This section describes only what is built, checked against the product on 22 November 2026.

**Material.** Material is issued to a work order from the [stock ledger](https://zudoworks.com/zmos/stock-ledger/) at the item’s real cost, and a return credits the same job. An over-issue, or an item that is not on the bill of materials, needs a reason. With inventory posting switched on in the accounting settings, which is the default, each job issue also posts a journal: it debits the Work in Progress account and credits Inventory Asset. A return reverses it. So the Work in Progress balance in the accounts moves with the floor, not at month end.

**Labour.** Hours are logged on the job at an hourly rate. The job page shows material, labour and total cost to date while the job is open, and the cost per unit once it closes.

![ZMOS job page for an open sample job. The labour panel shows 6.5 labour hours at an hourly rate of 48 US dollars with operations laser cut, bend, assemble and pack. The job cost panel shows material 400 dollars 51, labour 312 dollars and total 712 dollars 51, with per unit blank because the job is still open. Below it, a job issue stock movement lists the material issued](https://zudoworks.com/Asset/img/zmos/job-cost-card.webp)

Cost to date on an open job in ZMOS, with the job issue that put the material into work in progress. Sample data, captured from the product on 16 November 2026.

**Completion.** When the finished parts are received from the job, their value enters inventory. The material part comes out of Work in Progress, and the labour part, hours multiplied by the rate, is credited from a Job Labour account.

**Seeing the open jobs.** Work orders can be viewed as a board by status and as a calendar by due date, and status changes are written to the audit log. [Zudo AI](https://zudoworks.com/zudo-ai/) answers questions from the workspace data within the user’s role. Its formula library includes Little’s law for work in progress and lead time.

**Where it stops.** Three limits are worth stating plainly.

- The Work in Progress account in ZMOS holds the material in open jobs. Labour appears on each job’s cost panel and enters stock value when the job is completed. If you want labour in the WIP balance at month end, add it from the open-job list.
- Overhead allocation is not automated, and there is no standard costing with variances. ZMOS gives actual material and labour per job. Our comparison of [job costing in Zoho ERP and ZMOS](https://zudoworks.com/insights/zoho-erp-job-costing/) goes into this.
- WIP is tracked by job, not by process stage. A continuous process such as food or chemicals needs a different model.

The [job costing page](https://zudoworks.com/zmos/job-work-and-costing/) shows a full worked job. Startups and registered partners can [try ZMOS free](https://zudoworks.com/zmos/free-trial/) for six months. We also build on Zoho, and for a shop that already runs on it, job and WIP tracking in [Zoho Creator](https://zudoworks.com/zoho-creator-development/) is a common project.

## How to reduce WIP

Lists of ways to cut WIP are easy to find and mostly say the same things. In a small job shop, four actions do most of the work.

- **Do not release a job until it can run.** Check material, drawing and tooling first. A job released early does not finish early. It waits on the floor with cash in it.
- **Limit how many jobs are open at each work centre.** When the limit is reached, finish one before starting another.
- **Make smaller batches where set-up allows.** Half the batch is half the WIP and the first parts reach the customer sooner.
- **Chase the oldest jobs every week.** The ageing list tells you which. Most have a single missing thing.

Expect the first month of honest tracking to make the figure look worse. Jobs that were quietly forgotten appear on the list. That is the point of measuring it.

## What to take from this

WIP inventory is the cost of unfinished jobs. Calculate it with one line: opening WIP plus costs added, less the cost of jobs completed. Then prove it by adding up the open jobs, and investigate any gap. Watch WIP days and the age of the oldest jobs each week, agree with your accountant what cost includes at year end, and close jobs the day they finish. A shop that does those things knows how much cash is on its floor and which jobs are holding it.

## Frequently asked questions

## Frequently asked questions

What is WIP inventory?

WIP inventory is the cost of jobs that have started but are not finished. It includes the material issued to those jobs, the labour logged on them and any overhead applied. It sits between raw materials and finished goods, and it is shown as an asset on the balance sheet.

How do you calculate WIP inventory?

Closing WIP equals opening WIP, plus the manufacturing costs added in the period, minus the cost of jobs completed. Manufacturing costs added are material issued to jobs, labour logged and overhead applied. Check the answer by adding up the cost to date of every open job. The two totals should match.

Is it work in progress or work in process?

In manufacturing they mean the same thing and both shorten to WIP. Work in progress is the more common wording in Australia, New Zealand and the United Kingdom. Work in process is more common in the United States. Pick one for your shop and use it everywhere.

Is WIP an asset or an expense?

An asset, until the goods are sold. Costs in open jobs are held on the balance sheet as inventory. When a job is completed its cost moves to finished goods, and when the goods are delivered it becomes cost of goods sold, matched to the sale.

What are WIP days?

WIP days show how many days of production are sitting on the floor. Divide closing WIP by the cost of jobs completed in the period, then multiply by the days in the period. There is no universal target. Track your own trend, because rising WIP days mean jobs are taking longer to get through.

Does WIP include labour and overhead?

For management, many small shops count material and labour only. For year-end accounts, the Australian standard AASB 102 says the cost of conversion includes direct labour and a systematic share of production overheads based on normal capacity. Agree the method with your accountant and keep it consistent.

**Related services:** [Custom software](https://zudoworks.com/custom-software-development/) · [Zoho Creator development](https://zudoworks.com/zoho-creator-development/) · [Pricing](https://zudoworks.com/pricing/) · [Zoho development](https://zudoworks.com/zoho-development/)

![Arunkumar V](https://zudoworks.com/Asset/img/team/arunkumar-v-avatar.webp)

[Arunkumar V](https://zudoworks.com/about/arunkumar-v/), Founder and CTO, Zudo Works

Arunkumar builds ZMOS, Zoho Creator apps, Zoho CRM systems, Deluge automations and integrations for businesses in the US, UK, Australia, New Zealand and India. He received the Master of Creator award at the Zoho Creator Partner Hackathon 2025. Before founding Zudo Works in 2026 he worked at Teleperformance, at iOPEX Technologies and at a Zoho partner firm, and as a senior supervisor in manufacturing at Brakes India Private Limited, so he knows how a production floor runs.

[Arunkumar V on LinkedIn](https://www.linkedin.com/in/arunkumar-v-cto) [About Arunkumar](https://zudoworks.com/about/arunkumar-v/)

Zoho and the other product names in this article are trademarks of their respective owners. Facts about other products were checked against the vendors' own pages on the dates stated; tell us if something has changed.

## Related articles

[Zoho ERP Job Costing: What It Covers and Where It Stops](https://zudoworks.com/insights/zoho-erp-job-costing/)
[DIFOT: How to Calculate Delivery In Full, On Time](https://zudoworks.com/insights/difot-delivery-in-full-on-time/)
[BOM Revision Control: How to Change a Bill of Materials Without Breaking Production](https://zudoworks.com/insights/bom-revision-control/)
[Quoting Software for Manufacturing: A Job Shop Guide](https://zudoworks.com/insights/quoting-software-for-manufacturing/)